NTPC

 

bullet.gif (900 bytes) Details of Existing Generating Stations and their performance

bullet.gif (900 bytes) Details of Generating Stations under construction

 

 

 

 

 

 

 

Table : Details of Existing Generating Stations and their performance

S.No. Name of Station

Location

Installed Capacity
(No. of Units X MW)
Date of Commissioning Fuel Fuel Linkage

Performance during the year 1998-99

Region State / District Energy Generated (Mus) Energy Sent Out (Mus) PLF % Availability %
               

1

Singrauli STPS Northern   UP / Sonebadhra Unit I - 200 MW 13.02.82 Coal Jayant / Dudhichua mine, NCL        
Unit II - 200 MW 25.11.82
Unit III - 200 MW 28.03.83
Unit IV - 200 MW 02.11.83
Unit V - 200 MW 26.02.84
Unit VI - 500 MW 23.12.86
Units VII - 500 MW 24.11.87
                    Station - 2000 MW          

15797.8

   

91.28

2 Rihand STPS Northern UP / Sonebadhra Unit I - 500 MW 31.03.88 Coal Amiohri / Dudhichua Mine        
Unit II- 500 MW 05.07.89
        Station 1000 MW       6817.7     80.05
3. Dadri (Coal) Northern UP / Gautam Budh Nagar Unit I - 210 MW 21.12.91 Coal Pipariwar        
Unit II - 210 MW 18.12.92
Unit III - 210 MW 23.03.93
Unit IV - 210 MW 24.03.94
        Station - 840 MW       6727.5     94.83
4. Unchahar STPS Northern UP / Rai Bareilly Unit I - 210 MW 21.11.88 Coal North Karanpura        
Unit II - 210 MW 22.03.89
        Station 420 MW       3023.1     90.49
5. ANTA GPP Northern Rajasthan / Baran GT I - 88 MW 20.01.89 Gas          
GT II - 88 MW 04.03.89
GT III - 88 MW 04.05.89
ST I - 149 MW 05.03.90
        Station - 419 MW       2931.1      93.08
6. Auraiya GPP Northern UP / Auraiya GT I - 110 MW 29.03.89 Gas          
GT II - 110 MW 21.07.89
ST I - 106 MW 29.12.89
GT III - 110 MW 09.08.89
GT IV - 110 MW 29.09.89
ST - II 106 MW 12.06.90
        Station - 652 MW       4146.2     86.93
7. Dadri (Gas) Northern UP / Gautam Budh Nagar GT I - 131 MW 21.02.92 Gas          
GT II - 131 MW 26.03.92
GT III - 131 MW 16.06.92
GT IV - 131 MW 14.10.92
ST I - 146.5 MW 26.02.94
ST II - 146.5 MW 27.03.94
        Station - 817 MW       5099.2     92.15
8. Korba STPS Western MP / Jamnipali Unit I - 200 MW 01.03.83 Coal Gevra Mine        
Unit II - 200 MW 31.10.83
Unit III - 200 MW 17.03.84
Unit IV - 500 MW 31.05.87
Unit V - 500 MW 25.03.88
Unit VI - 500 MW 23.03.89
        Station - 2100 MW       16046.6     90.96
9. Vindhyachal STPS Western MP / Sidhi Unit I - 210 MW 10.10.87 Coal Nigahi / Dudhichua Mine        
Unit II - 210 MW 23.07.88
Unit III - 210 MW 03.02.89
Unit IV - 210 MW 26.12.89
Unit V - 210 MW 31.03.90
Unit VI - 210 MW 01.02.91
         Station - 1260 MW        9934.2     91.08
10. Kawas GPP Western Gujarat / Surat GT I - 106 MW 22.03.92 Gas          
GT II - 106 MW 24.05.92
GT III - 106 MW 30.06.92
GT IV - 106 MW 27.08.92
ST I - 110.5 MW 23.02.93
ST II - 110.5 MW 19.03.93
        Station - 645 MW       4411.9     90.57
11. Jhanor-Gandhar GPP Western Gujarat / Bharuch GT I - 131 MW 17.03.94 Gas          
GT II - 131 MW 31.03.94
GT III - 131 MW 20.05.94
ST I - 255 MW 30.03.95
        Station - 648 MW       2162.2     75.93
12. Ramagundam STPS Southern AP / Karimnagar Unit I - 200 MW 26.11.83 Coal Ramagundam area of Singareni Colleries Co. Ltd.        
Unit II - 200 MW 29.05.84
Unit III - 200 MW 13.12.84
Unit IV - 500 MW 26.06.88
Unit V - 500 MW 26.03.89
Unit VI - 500 MW 16.10.89
        Station - 2100 MW         15859.2       89.36
13. Kayamkulam GPP Southern Kerala / Allepey GT I - 115 MW 05.11.98 Gas          
GT II - 115 MW 28.02.99
        Station - 230 MW       177.8     83.26
14. Farakka STPS Eastern West Bengal / Mushirabad Unit I - 200 MW 01.01.86 Coal Rajmahal Mine        
Unit II - 200 MW 24.12.86
Unit III - 200 MW 06.08.87
Unit IV - 500 MW 25.09.92
Unit V - 500 MW 16.02.94
        Station - 1600 MW       5475.6     81.51
15. Kahalgaon STPS Eastern Bihar / Bhagalpur Unit I - 210 MW 31.03.92 Coal Rajmahal Mine            
Unit II - 210 MW 17.03.94
Unit III - 210 MW 24.03.95
Unit IV - 210 MW 18.03.96
        Station - 840 MW       3988.7     91.24
16. Talcher STPS Eastern Orissa / Angul Unit I - 500 MW 19.02.95 Coal Lingraj Mine        
Unit II - 500 MW 27.03.96
        Station - 1000 MW       4592.5     95.28
17. Talcher TPS (Old) Eastern Orissa / Angul Unit I - 60 MW 17.12.67 Coal Jagannath Mine / Lingraj Expantion Mine        
Unit II - 60 MW 28.03.68
Unit III - 60 MW 11.07.68
Unit IV - 60 MW 11.04.69
Unit V - 110 MW 24.03.82
Unit VI - 110 MW 24.03.83
        Station - 460 MW       2248.5     83.1


1. Energy Generated (Mus) - Energy generated at the generatory terminals (gross energy).
2. Energy Sent Out (MUs) - Energy injected into the grid (energy generated - Aux. Consumption)
3. Plant Load Factor (PLF) %- The ratio of actual energy generated during the period and the max. energy generated. This could have been at rated installed capacity during the period.
4. Availability % - The ratio of capability of generating station in MW during the period and the installed capacity of the generating station.

 

Table : Details of Generating Stations under construction

S.No. Name of Station

Location

Installed Capacity
(No. Of Units x MW)
Fuel Target Date of Commissioning
Region State/District

1.

Vindhyachal
Stage II
Western MP / Sidhi 2 x 500 Coal Unit VII - May '00
Unit VIII - May '01
2. Unchahar
Stage II
Northern UP /Rai Bareilly 2 x 210 Coal Unit III - Apr '00
Unit IV - Oct '00
3. Faridabad
CCPP
Northern Haryana / Faridabad GT 2 x 143 +
1x144 ST
Gas GT I -Aug '99
GT II - Mar '00
ST - Jan '01
4. Kayamkulam
CCPP
Southern Kerala / Allepey GT 2 x 115 +
1 x 120 ST
Naptha GT I - Commissioned
GT II - Commissioned
ST - Mar '00
5. Simhadri, TPP Southern AP / Vishakhapatnam 2 x 500 Coal Unit I - Jun '02
Unit II - Mar '03

 

 


 