Table : Details of Existing Generating Stations and their performance.

S.No.

Name of Station &
Type of Scheme

Location

Installed Capacity
(No. Of Units X MW)

Date of
Commissioning

Performance during the year 1998-99

Region

State / District

Energy
Generated (Mus)

Energy Sent
Out (Mus)

Design Energy

Availability %

           

1

Baira Siul Hep
Run of River

Northern

H.P./Chamba

Unit I - 60 MW

18.05.80

330.19

}

250

}

Unit II - 60 MW

19.05.80

256.27

} 733.54

250

} 74.53

Unit III - 60 MW

13.09.81

163.81

}

250

}

       

Station 180 MW

         

2

Chamera HEP
Run of River

Northern

H.P./Chamba

Unit I - 180 MW

28.04.94

686.6

}

554.67

}

Unit II - 180 MW

25.04.94

768.31

} 2352.36

554.67

} 82.09

Unit III - 180 MW

22.04.94

912.37

}

554.67

}

       

Station 540 MW

         

3

Tanakpur HEP
Run of River

Northern

UP / Udhamsingh
Nagar

Unit I - 31.4 MW

31.03.92

182.5

}

153.3

}

Unit II - 31.4 MW

04.04.92

130.88

} 465.77

153.3

} 87.70

Unit III - 31.4 MW

04.04.92

155.95

}

153.3

}

       

Station 94 MW

         

4

Salal HEP
Run of River

Northern

J&K/Udhampur

Unit I - 115 MW

09.11.87

472.24

}

679.33

}

Unit II - 115 MW

14.11.87

551.98

}

679.33

}

Unit III - 115 MW

20.11.87

477.24

}

679.33

}

Unit IV - 115 MW

31.03.93

543.79

} 3189.25

354.2

} 91.19

Unit V - 115 MW

29.05.94

642.67

}

354.2

}

Unit VI - 115 MW

23.02.95

534.75

}

354.2

}

       

Station 690 MW

         

5

Uri HEP
Run of River

Northern

J&K/Baramulla

Unit I - 120 MW

10.04.97

664.69

}

665.85

}

Unit II - 120 MW

03.03.97

696.92

}

665.85

}

Unit III - 120 MW

27.01.97

617.4

} 2550.12

665.85

} 96.21

Unit IV - 120 MW

13.03.97

596

}

665.85

}

       

Station 480 MW

         

6

Loktak HEP
Natural Storage

 

Manipur / Bishanpur
& Churachandpur

Unit I - 35 MW

29.05.83

211.18

}

150

}

Unit II - 35 MW

30.04.83

190.79

} 529.15

150

} 93.48

Unit III - 35 MW

13.05.83

130.45

}

150

}

       

Station 105 MW

          


Table : Details of Generating Stations under construction

S.No.

Name of Station
& Type of Scheme

Location

Installed Capacity
(No. Of Units X MW)

Target Date
of Commissioning

Region

State / District

1

Rangit
Run of River

NER

Sikkim / South Sikkim

3 x 20 = 60

Nov. 99

2

Dulhasti
Run of River

Northern

J&K/Doda

3 x 130 = 390

Mar '01

3

Dhauliganga - I
Run of River

Northern

UP / Pitthoragarh

4 x 70 = 280

Sep ' 04

4

Chamera - II
Run of River

Northern

H.P./Chamba

3 x 100 = 300

May ' 04

 

 


 

[Home] [About Us] [Extracts of Acts]
[Regulations][Orders] [Publications] [Power Data] [Annual Report]
[Schedule of Hearings][Bulletin Board] [Jobs] [Contact Us] [Search] [Links]  .