NEEPCO
Details of Existing Generating Stations
and their performance
Details of Generating Stations under
construction
Table : Details of Existing Generating Stations and their performance.
Thermal Projects
S.No. |
Name of station |
Location |
Installed Capacity |
Date of commissioning |
Fuel |
Fuel Linkage |
Performance during the year 1998-99 |
||||
Region |
(State / District) |
Energy generated (Mus) |
Energy sent out(Mus) |
PLF% |
Availablity% |
||||||
1 |
Assam gas based power project |
North Eastern |
Assam / Bokuloni |
GTU - I 33.5 MW |
Mar-95 |
Natural Gas |
|||||
GTU - II 33.5 MW |
Mar-95 |
||||||||||
GTU - III 33.5 MW |
Jun-95 |
||||||||||
GTU - IV 33.5 MW |
Jul-95 |
||||||||||
GTU - V 33.5 MW |
Mar-96 |
||||||||||
GTU - VI 33.5 MW |
Oct-96 |
||||||||||
STU - I 30 MW |
Mar-98 |
||||||||||
STU - II 30 MW |
Mar-98 |
||||||||||
STU - III 30 MW |
Jul-98 |
||||||||||
STATION - 291 MW |
743.35 |
743.35 |
43.80% |
||||||||
2 |
Agartala gas Turbine Project |
North Eastern |
Tripura Ramchandranagar |
GTU - I 21 MW |
Feb-98 |
Natural Gas |
|||||
GTU - II 21 MW |
Feb-98 |
||||||||||
GTU - III 21 MW |
Mar-98 |
||||||||||
GTU - IV 21 MW |
Mar-98 |
||||||||||
STATION - 84 MW |
197.205 |
197.205 |
39.50% |
Hydro Projects
S.No. |
Name of Station & Type of scheme |
Location |
Installed Capacity (No. of unitsXMW) |
Date of commissioning |
Performance during the Year 1998-99 |
||||
Region |
State / District |
Energy generated (Mus) |
Energy sent out (Mus) |
Design Energy |
Availablity % |
||||
(a) |
Kopili He Proj.Khandong Power House |
North Eastern |
Assam / Hills |
Unit1- 25 MW |
Mar-88 |
||||
1 |
Unit2- 25 Mw |
Mar-88 |
|||||||
(b) |
Kopili Power House |
Unit 1 - 50 MW |
Mar-98 |
||||||
Unit 2 - 50 MW |
Mar-98 |
||||||||
STATION - 150 MW |
556.45 |
556.45 |
|||||||
2 |
KHEP Stage - 1 Extn Kopili Power House |
North Eastern |
Assam / Hills |
Unit - 3 50 MW |
Mar-97 |
||||
Unit - 4 50 MW |
Jun-97 |
||||||||
STATION - 150 MW |
438.72 |
438.72 |
Note : The data as furnished by NLC has been reproduced. The Commission has not verified it.
Table : Details of
Generating Stations under construction
S.No. |
Name of Station & Type of Scheme |
Location |
Installed Capacity (No of unitsXMW |
Target date of Commissioning |
|
Region |
State / District |
||||
1 |
Doynag H.E. Project |
North Eastern |
Nagaland / Wokha |
Unit - 1 25 MW |
Mar '00 |
Unit - 2 25 MW |
Mar '00 |
||||
Unit - 3 25 MW |
Mar '00 |
||||
2 |
Ranganadi H.E.Project |
North Eastern |
Arunachal Pradesh |
Unit - 1 135 Mw |
Mar '01 |
Unit - 2 135 Mw |
Aug '01 |
||||
Unit - 3 135 Mw |
Sep '01 |
||||
3 |
Tuirial H.E. Project |
North Eastern |
Mizoram |
Unit - 1 30 MW |
Jun '06 |
Unit - 2 30 MW |
Jun ' 06 |
||||
4 |
Kopili H.E.Proj 2nd Stage |
North Eastern |
Assam |
Unit - 1 25 MW |
Jul '03 |